Sangamon Right of Way Photo Slide Show
Sangamon Right of Way Photo slideshow
-

The topsoil was hydro seeded at the end of the action.
-

The excavated areas were backfilled with 18 inches of stone and 6 inches of topsoil.
-

The excavated areas were backfilled with 18 inches of stone and 6 inches of topsoil.
-

EPA will oversee removal action by BNSF along the Sangamon right-of-way between 18th and 21st Streets. The right-of-way runs between private properties on the east (left) and the city sidewalk or street to the west (right).
-

Fencing being installed bordering the area between Cullerton and 21st Street along the right of way. Fencing will prevent access to the cleanup areas.
-

Loading contaminated soil onto truck for disposal
-

Adding and blending of treatment product into hazardous lead area
-

Removal of BNSF steel rails and ties between 16th and 18th Streets
-

Grading of gravel across the site
